GANTTRIGHT TEMPLATES
====================

115 starting plans across 45 industries, one folder each. Open the closest one,
rename the tasks to match your own work, and drag the blocks where they belong.
Nothing here is a form to fill in - it is a plan you edit.


WHAT THESE CARRY, AND WHAT THEY DO NOT
--------------------------------------

The sequence is the useful part. Which step blocks which, where the hard gates
sit, and what can safely run alongside something else - that is what these
templates hold, and it is the part that takes years to learn and minutes to get
wrong.

The numbers are a starting shape, not an industry benchmark. Durations are
plausible rather than researched. Hours per period were chosen so the Resource
Load graph shows something sensible. Replace both with your own the first time
you use a template: you know your crew, your suppliers and your site better than
any template can.

Some waits genuinely are fixed, and those are worth keeping. Statutory
determination periods, curing and clearance times, manufacturing lead times,
laboratory incubation - where a duration is a real constant rather than an
estimate, the task note says so.


HOW A TEMPLATE IS BUILT
-----------------------

  Pink blocks    Critical work. The spine of the plan. If one of these slips,
                 the finish date slips with it.
  Green blocks   Work with room to move. The arrows on either side show how far
                 it can slide before it starts to matter.
  Diamonds       Milestones. The moments the plan is measured against - a permit
                 granted, a design frozen, a certificate issued.
  The last one   Project Finish. Drawn as a line the full height of the chart,
                 because it is not one row's business.

Trades and Shutdown plans are measured in days, because that is how those jobs
are quoted. The rest are in weeks. Work never lands on a shaded weekend in
either. Leads are fictional. Every task carries a note saying why that step is
there and what it blocks; open the Task Inspector to read them.


FOLDERS AND NAMING
------------------

  Templates/<Industry>/GanttRight_Template_<Industry>_<Project>.gtrt

Keep the pattern if you add your own.


ALL TEMPLATES
-------------

INDUSTRY         PROJECT                                   SPAN  TASKS
-----------------------------------------------------------------------
Accounting       Busy Season Plan                       28 weeks     15

Agency           Website Redesign                       18 weeks     14

Agriculture      Crop Season Plan                       34 weeks     15

Architecture     Building Design Package                30 weeks     15

Aviation         Cabin Refit                            34 weeks     12
                 Fleet Introduction                     44 weeks     12
                 Heavy Maintenance Check                26 weeks     13

Banking          Regulatory Reporting Change            26 weeks     14

Broadcast        Documentary Production                 38 weeks     13
                 Live Event Broadcast                   19 days     13
                 Studio Build                           30 weeks     12

Compliance       SOC 2 Certification                    32 weeks     14

Construction     Apartment Development                  52 weeks     15
                 Basement Excavation                    32 weeks     13
                 Bridge Refurbishment                   34 weeks     14
                 Custom Home Build                      44 weeks     16
                 Hotel Refurbishment                    30 weeks     13
                 Office Fit-Out                         26 weeks     14
                 Retail Fit-Out                         24 weeks     15
                 Road Resurfacing                       20 weeks     13
                 School Extension                       34 weeks     13
                 Warehouse New Build                    48 weeks     15

E-commerce       Peak Season Readiness                  26 weeks     15

Education        Online Course Launch                   20 weeks     13

Energy           Solar Installation                     30 weeks     15

Events           Annual Conference                      28 weeks     21

Film             Short Film Production                  20 weeks     15

Finance          Year End Audit                         20 weeks     15

Franchise        Brand Refresh Rollout                  34 weeks     11
                 Franchisee Onboarding                  20 weeks     12
                 New Location Opening                   26 weeks     13

Games            Game Launch                            28 weeks     15

HR               Executive Search                       24 weeks     15

Healthcare       Clinic Opening                         28 weeks     14

Hospitality      Restaurant Opening                     26 weeks     14

IT               ERP Implementation                     36 weeks     15

Insurance        Claims System Migration                36 weeks     15

Legal            M&A Deal Close                         22 weeks     14

Logistics        Warehouse Relocation                   28 weeks     15

Manufacturing    New Product Introduction               30 weeks     15

Marine           Boat Refit                             20 weeks     12
                 Dry Dock Survey                        17 days     12
                 Yacht Interior Refit                   26 weeks     12

Marketing        Brand Refresh                          30 weeks     14
                 Content Marketing Program              28 weeks     13
                 Customer Referral Program              22 weeks     13
                 Email Automation Build                 20 weeks     13
                 Influencer Campaign                    22 weeks     13
                 Launch Paid Search                     22 weeks     16
                 Product Launch Campaign                24 weeks     15
                 SEO Overhaul                           30 weeks     13
                 Trade Show Exhibition                  26 weeks     14
                 Video Ad Production                    18 weeks     13

Mining           Mine Closure & Rehabilitation          44 weeks     12
                 Processing Plant Upgrade               34 weeks     11
                 Shaft Sinking                          48 weeks     13

Municipal        Leisure Center Refurbishment           30 weeks     12
                 Park Redevelopment                     36 weeks     12
                 Road Safety Scheme                     34 weeks     12

Museum           Collection Move                        34 weeks     12
                 Exhibition Install                     30 weeks     12
                 Gallery Redevelopment                  40 weeks     12

Nonprofit        Fundraising Gala                       26 weeks     15

Pharma           Clinical Trial Phase II                40 weeks     15

Public Sector    Procurement Tender                     30 weeks     15

Publishing       Book Launch                            34 weeks     15

Rail             Possession Works                       17 days     12
                 Signaling Renewal                      40 weeks     11
                 Station Refurbishment                  30 weeks     11

Real Estate      Property Renovation                    24 weeks     15

Recruitment      Client Onboarding                      16 weeks     14

Research         Grant Funded Study                     32 weeks     14

Shutdown         Brewery Annual Maintenance             17 days     13
                 Chemical Plant Shutdown                32 weeks     15
                 Data Center Maintenance Window         17 days     13
                 Food Plant Deep Clean                  15 days     13
                 Furnace Reline                         30 weeks     14
                 Offshore Platform Shutdown             28 weeks     13
                 Paper Mill Shutdown                    22 days     13
                 Power Station Outage                   34 weeks     15
                 Refinery Turnaround                    40 weeks     18
                 Water Treatment Outage                 19 days     13

Software         API Platform Launch                    26 weeks     14
                 Accessibility Compliance               24 weeks     13
                 Cloud Migration                        32 weeks     15
                 Data Platform Build                    30 weeks     13
                 Design System Rollout                  28 weeks     13
                 Legacy System Rewrite                  44 weeks     14
                 Major Version Upgrade                  22 weeks     13
                 Mobile App Release                     22 weeks     16
                 SaaS MVP Launch                        24 weeks     15
                 Security Remediation                   26 weeks     14

Sports           Season Launch                          24 weeks     12
                 Stadium Event Turnaround               15 days     13
                 Youth Academy Setup                    34 weeks     13

Theatre          Stage Production                       22 weeks     12
                 Touring Production                     26 weeks     12
                 Venue Refurbishment                    32 weeks     12

Trades           Asbestos Removal                       19 days     13
                 Bathroom Renovation                    23 days     13
                 EV Charger Installation                29 days     13
                 Electrical Rewire                      23 days     13
                 Fire Alarm Installation                31 days     14
                 HVAC Installation                      37 days     14
                 Heat Pump Installation                 43 days     15
                 Kitchen Installation                   37 days     16
                 Landscaping Project                    29 days     13
                 Loft Conversion                        57 days     16
                 Plumbing Repipe                        19 days     13
                 Roofing Replacement                    19 days     13
                 Window & Door Replacement              47 days     14

Veterinary       Imaging Equipment Upgrade              20 weeks     13
                 Practice Accreditation                 24 weeks     12
                 Practice Opening                       30 weeks     12

Weddings         Wedding Planning                       40 weeks     17


STARTING FROM ONE
-----------------

1. Open the template closest to your work.
2. Save As under your own project name before changing anything.
3. Rename tasks and leads. Keep the shape - the dependencies are the useful part.
4. Put your own durations in. The ones here are a starting shape.
5. Drag blocks to your dates. Anything pink pushes what follows it; anything
   green slides within the room its arrows show.
6. Turn on Resource Load to see whether one person is carrying three jobs in the
   same week.

The fastest way to learn the chart is to drag a pink block and watch what moves.